Branich Tunnel

Completed projects

Find out more

Gallery

Branich Tunnel

NOE Reference: Branich Tunnel

The short assembly times and the essentially self-explanatory design were particularly impressive. The fitters required seven working days each to assemble the slab formwork carriage and the reinforcement formwork carriage. Furthermore, both NOEtec carriages were designed in such a way that the commercial vehicles required on the construction site could pass underneath them unhindered, thus ensuring that tunnel construction operations were not disrupted.  

Project details

Period

2016

Purpose

As part of the Schriesheim bypass, construction is underway on the 1,796-metre-long Branich Tunnel

Formwork systems

NOEtec slab formwork trolley, approx. 10 metres long, 9.6 metres wide and 6 metres high, capable of carrying a load of approx. 60 tonnes 

NOEtec reinforcement trolley, 10 m long, approx. 14 m wide and 9 m high

NOEtop with integrated strapping

NOE H20 timber joists as secondary beams for NOEform formwork facings

NOE LS 200 heavy-duty props

Special features

The NOEtec system was used to solve two completely different tasks. As time is always at a premium on any construction site, the technicians at NOE ensured that the reinforcement trolley did not have to be completely dismantled in order to manoeuvre it through the narrower standard clearance to the next emergency lay-by. For this reason, they designed the reinforcement trolley so that the upper working platform could be lowered and the middle one folded in sideways.

Clients

State of Baden-Württemberg, Karlsruhe Regional Council

Contractor

Ed. Züblin AG, Stuttgart 