Home Formwork technology References Tunnel construction Branich Tunnel
The short assembly times and the essentially self-explanatory design were particularly impressive. The fitters required seven working days each to assemble the slab formwork carriage and the reinforcement formwork carriage. Furthermore, both NOEtec carriages were designed in such a way that the commercial vehicles required on the construction site could pass underneath them unhindered, thus ensuring that tunnel construction operations were not disrupted.
Period
2016
Purpose
As part of the Schriesheim bypass, construction is underway on the 1,796-metre-long Branich Tunnel
Formwork systems
NOEtec slab formwork trolley, approx. 10 metres long, 9.6 metres wide and 6 metres high, capable of carrying a load of approx. 60 tonnes
NOEtec reinforcement trolley, 10 m long, approx. 14 m wide and 9 m high
NOEtop with integrated strapping
NOE H20 timber joists as secondary beams for NOEform formwork facings
NOE LS 200 heavy-duty props
Special features
The NOEtec system was used to solve two completely different tasks. As time is always at a premium on any construction site, the technicians at NOE ensured that the reinforcement trolley did not have to be completely dismantled in order to manoeuvre it through the narrower standard clearance to the next emergency lay-by. For this reason, they designed the reinforcement trolley so that the upper working platform could be lowered and the middle one folded in sideways.
Clients
State of Baden-Württemberg, Karlsruhe Regional Council
Contractor
Ed. Züblin AG, Stuttgart